Pay less notice template (UK): payment notices, deadlines and examples

A pay less notice tells the person you owe that you'll pay less than the notified sum, and why. Under the Construction Act it must state the sum you think is due and how you worked it out. It must arrive by the deadline in your contract or, if the contract is silent, no later than 7 days before the final date for payment. Miss it, and you must pay the notified sum in full by the final date. Templates for all three notices are below, to copy or download free as Word documents.

In short

  • Paying less than the notified sum? Send a pay less notice with the figure you think is due and how you got there.
  • The deadline is in your contract. If it says nothing, the notice must arrive no later than 7 days before the final date for payment.
  • No valid notice in time means the notified sum is due in full by the final date. If it isn't paid, the person owed can suspend work after giving at least 7 days' notice, or refer the dispute to adjudication.
  • The payer's payment notice is due no later than 5 days after the payment due date. If you're the one being paid and it doesn't arrive, send your payee's notice straight away.
  • These rules don't cover work on a home the customer lives in or plans to live in.

What is a pay less notice?

A pay less notice is the payer's formal notice that they intend to pay less than the notified sum. The notified sum is the figure in the payment notice (or in the payee's own notice, if the payer never sent one). Section 111 of the Housing Grants, Construction and Regeneration Act 1996, as amended in 2011, says the payer must pay the notified sum on or before the final date for payment, unless a valid pay less notice has been given in time.

Before October 2011 (November 2011 in Scotland) the same job was done by a "notice of intention to withhold payment", which is why you still hear people call it a withholding notice.

There are three notices: the payer's payment notice (what they think is owed), the payee's notice (yours, if the contract says so or the payer's never came) and the pay less notice. All three can state a sum of zero, as long as they give the sum and the basis for it.

Who sends which notice, and when?

The contract sets the dates. The Act only sets the rules the contract has to follow, and the Scheme for Construction Contracts fills any gap.

Notice Who sends it Deadline What it must say Law
Payment notice Payer or a specified person Not later than 5 days after the payment due date The sum they consider due at the due date, and the basis of the calculation s.110A(1)(a), (2)
Payee's notice (contract route) You, if the contract puts the notice on you Not later than 5 days after the payment due date The sum you consider due, and the basis of the calculation s.110A(1)(b), (3)
Payee's notice in default You, when the payer's notice doesn't arrive Any time after the payer's deadline has passed The sum you consider due, and the basis of the calculation s.110B
Pay less notice Payer or a specified person The period agreed in the contract before the final date, or 7 days before it if nothing is agreed The sum they consider due on the date of the notice, and the basis of the calculation s.111(3) to (7), Scheme para 10
Notice to suspend work You, if the notified sum isn't paid by the final date At least 7 days before you suspend The grounds for suspending s.112

Two details trip people up. First, if you send a payee's notice in default, the final date for payment moves back by the number of days your notice was late. Send it the next day. Second, if your contract lets you apply for payment before the payer's notice is due, and you apply properly, that application counts as your payee's notice (s.110B(4)). A good application does double duty.

What are the default dates if the contract says nothing?

The Scheme for Construction Contracts (England and Wales) sets them. For stage payments, the valuation period is 28 days unless the contract says otherwise. The payment becomes due 7 days after the end of that period, or when you make your claim, whichever is later. The final date for payment is 17 days after the due date.

Here's how that plays out if your valuation period ends on 31 October and your claim is in by then. The dates are an illustration of the Scheme timings, not a rule for your contract.

Day Date What happens
0 31 October Valuation period ends, your claim is in
7 7 November Payment due date
12 12 November Last day for the payer's payment notice
13 onwards From 13 November If no payment notice arrived, send your payee's notice straight away
17 17 November Last day for a pay less notice (7 days before the final date)
24 24 November Final date for payment of the notified sum
25 onwards From 25 November Unpaid? Give at least 7 days' notice to suspend, or refer to adjudication

Most written contracts set their own periods, so check yours before you rely on these. Put the contract's own dates in the diary the day you sign, one line per valuation.

What does a pay less notice need to include?

Two things by law: the sum the payer considers due on the date the notice is served, and the basis on which it's calculated. A usable pay less notice also shows:

  • the contract, the job and the valuation or application it responds to
  • the notified sum it's reducing
  • each deduction on its own line, with the reason (defects, a disputed variation, contra charges)
  • the sum that will be paid by the final date
  • who it's from, and the date it was sent

Check your contract's notice clause for how notices must be served (email, post or by hand). A notice sent the wrong way can be argued to be no notice at all.

How do you send a pay less notice?

Follow your contract first. The Act lets both sides agree how notices are sent, so check the notices clause for the method and the address or email it names.

If the contract says nothing, the Act says any method that works will do, as long as it's in writing (section 115). A notice sent by post to the right address, and delivered, counts as served. The right address is:

  • for a company, its registered office or main office;
  • for a sole trader or partnership, their last known main business address.

Three habits keep a notice safe:

  • Put it in writing. A phone call or a word on site isn't a notice.
  • Send it early. Aim for a day or two before the deadline, not the last day. When you count the days, leave out Christmas Day, Good Friday and bank holidays (section 116).
  • Keep proof it arrived. Use a tracked, signed-for post service, keep the sent email with its date and time, or get a signature if you hand it over.

It must come from the payer, or from the person the contract names to give notices on the payer's behalf. In Northern Ireland, Article 14 of the 1997 Order sets the same basic rules: agree the method in the contract, or use any method that works, in writing.

Pay less notice template

Copy this, fill in the brackets, and delete what doesn't apply.

Prefer Word? Download the pay less notice template (a free Word document, no email needed).

Pay less notice

Section 111 of the Housing Grants, Construction and Regeneration Act 1996

From: [payer's company name and address]
To: [payee's company name and address]
Date of this notice: [date]

Contract: [contract name and date]
Project: [site address and job reference]
Payment: [valuation or application number], payment due date [date], final date for payment [date]

Notified sum: £[amount], as stated in [your payment notice / the payee's notice] dated [date]

We intend to pay less than the notified sum.

The sum we consider due on the date of this notice is £[amount].

Basis of calculation:
Gross value of work to date as applied: £[amount]
Less [item and reason, e.g. variation 4 not instructed, see email dated]: £[amount]
Less [item and reason, e.g. defective work at plot 12, photos attached]: £[amount]
Less retention at [x]%: £[amount]
Less previous payments: £[amount]
Sum due: £[amount]

Signed: [name, position]

Payment notice and payee's notice templates

The payment notice is the payer's. The payee's notice is yours, and it should carry the same working as your application.

Both are free to download as Word documents: payment notice template and payee's notice template.

Payment notice

Section 110A of the Housing Grants, Construction and Regeneration Act 1996

From: [payer or specified person] To: [payee] Date: [date]
Contract and project: [contract, site, job reference]
Payment: [valuation number], due date [date], final date for payment [date]

The sum we consider due at the payment due date is £[amount].
Basis of calculation: [gross value to date, less retention, less previous payments, as attached]

Signed: [name, position]

Payee's notice

Sections 110A(3) and 110B of the Housing Grants, Construction and Regeneration Act 1996

From: [your business name and address]
To: [payer's company name and address]
Date of this notice: [date]

Contract and project: [contract, site, job reference]
Payment: [valuation or application number], payment due date [date]

[If sent in default: No payment notice was received by [date], the last day for one under the contract.]

The sum we consider due at the payment due date is £[amount].

Basis of calculation:
Work to date as per the attached valuation: £[amount]
Agreed variations [numbers]: £[amount]
Less retention at [x]%: £[amount]
Less previous payments: £[amount]
Sum due: £[amount]

Signed: [name, position]

What happens if no payment notice is issued?

You can send your own payee's notice instead. If the payer's payment notice hasn't arrived by the contract's deadline, the Act lets you give a payee's notice in default at any time after that deadline has passed (s.110B). It gives the sum you consider due and the basis of the calculation. That sum becomes the notified sum. The payer must pay it by the final date unless they send a valid pay less notice in time.

Don't wait. The final date for payment moves back by the number of days your notice was late, so a notice sent a week late pushes the final date back a week. Use the payee's notice template above, with the line for a notice sent in default.

One exception: if your contract let you apply for payment before the payer's notice was due, and you applied as the contract says, your application already counts as your payee's notice (s.110B(4)). You can't give a second one.

What happens if the pay less notice is late or never sent?

The payer has to pay the notified sum in full by the final date. They can still argue about the value later, but not by holding back money now. If they don't pay, you have two routes under the Act:

  • Suspend. You can suspend any or all of your work after giving at least 7 days' notice stating your grounds. The payer is liable for your reasonable costs of suspending, and the time you're off site doesn't count against your programme.
  • Adjudicate. Either side can refer a dispute to adjudication at any time. The adjudicator must decide within 28 days of the referral, unless the time is extended. If they decide more is owed than the payer's notice said, the extra is due within 7 days of the decision or by the original final date, whichever is later.

Retention sits inside these same rules, and so does chasing its release. That's covered in our guide to retention in construction. If a payer just ignores the lot, the same steps as chasing any unpaid invoice apply, and between businesses you can add late payment interest.

Do payment notices apply to homeowner jobs?

No. Section 106 says this part of the Act doesn't apply to a contract with a residential occupier, meaning work mainly on a house or flat that the customer lives in or plans to live in. Work for a developer or landlord on homes they don't live in generally falls inside it. For a kitchen or rewire at someone's own home, the payment terms are whatever you agreed. Put stage payments and due dates in the quote, and see our guide to deposits and stage payments for building work.

The dates on this page come from the Scheme for England and Wales. Scotland has its own Scheme for Construction Contracts, so check that one for Scottish jobs.

In Northern Ireland the same three notices come from the Construction Contracts (Northern Ireland) Order 1997, as amended from 14 November 2012. Article 9A covers payment notices, Article 9B the payee's notice in default and Article 10 pay less notices. The Scheme for Construction Contracts in Northern Ireland sets the same default dates: a 28-day valuation period, payment due 7 days after the period ends or when you make your claim (whichever is later), a final date 17 days after the due date, a payment notice no later than 5 days after the due date and a pay less notice no later than 7 days before the final date. On a Northern Ireland job, quote the Order instead of the Act at the top of each template. For example, a pay less notice cites Article 10 of the Construction Contracts (Northern Ireland) Order 1997 instead of section 111.

Why do subcontractors lose money on notices?

Because the windows are short and they land while you're on site. Send your notice late and your final date slides. Miss a pay less notice on your own subbies and you pay them in full, dispute or not.

Kade Dillon spent 15+ years in construction before he co-founded Nexley. The point, in his words, is to "take those jobs on with the absolute full confidence that you will not be caught up going back and forth with the main contractor, not get caught up taking on risks that you weren't aware of." Notices done on time are most of that.

Where Nexley fits

Nexley is the AI back office for UK trade firms. Five AI assistants do the office work overnight, and you approve each one from WhatsApp. It handles the diary, invoicing, automatic quote and invoice chasing and document filing, and works with Xero, QuickBooks or Sage. Send a voice note when the contract lands and it can put every due date, notice deadline and final date in the diary. Tell it what's been done this period and it drafts your application or notice to your standard, for you to sign off before anything goes. When a final date passes unpaid, it chases, in your words. Anything it isn't sure of comes back to you on WhatsApp.

See how it keeps cash coming in on the cashflow and Xero page, what else it takes off your plate on the back office page, or try it free for 7 days.

Common questions

Can a pay less notice be for zero?

Yes. The Act says it doesn't matter that the sum stated may be zero, as long as the notice gives the sum and the basis on which it was worked out. The same goes for a payment notice or a payee's notice. A zero notice still has to arrive in time and show how you got to that figure. Listing each deduction with its reason is the clearest way to do that.

How many days before the final date must a pay less notice be sent?

Whatever your contract says. If the contract doesn't set a period, the Scheme says no later than 7 days before the final date for payment. Under the Scheme's default dates, the final date is 17 days after the payment due date, so the last day for a pay less notice is 10 days after the due date. Most written contracts set their own periods, so check yours and put the dates in the diary.

Is a pay less notice the same as a withholding notice?

It does the same job. "Notice of intention to withhold payment" was the wording in section 111 before the 2011 changes. The new rules apply to contracts made on or after 1 October 2011 in England and Wales, or 1 November 2011 in Scotland. In Northern Ireland the same change came in on 14 November 2012.

Sources

This page is general guidance, not legal advice. For a large or disputed sum, get your contract and notices checked.

Topic: Getting paid

Keep reading

Getting paid

How to know if a job made money: job costing for trades

Most trade owners find out a job lost money months later, if ever. This guide shows the four costs to track per job, with a quoted-versus-actual worked example on a garage conversion and a calculator for your last job.

29 Oct 2026, 6 min read, Kade Dillon

Getting paid

Matching supplier invoices to jobs in Xero

Supplier bills only tell you about a job if they're coded to it. This guide sets up job tracking in Xero, works through splitting one merchant invoice across three jobs, and gives you a weekly checklist.

29 Oct 2026, 6 min read, Kade Dillon

Try it on your own jobs

7 days free, then £799 a month. No contract.

Runs in WhatsApp Set up on a 20-minute call Cancel anytime
Saves me so much time every week. Does internal organisation and admin, but also when a customer messages in, Nexley replies, books them in against when I’ve got time to do it, and gets the invoice sorted in Xero.”
— Ollie Cable

Book a demo with Kade

A 20-minute call. Pick a time that suits and he’ll show you Nexley on your own work.

WhatsApp Us