Tendering and estimating, 29 October 2026

Reading a tender pack in 10 minutes: what to pull out first

Read a tender pack in this order: the instructions to tenderers for the deadline and what to return, the scope and drawings list, the form of contract and its amendments, payment terms and retention, the scoring criteria, then anything that rules you out. Ten minutes on those tells you whether to bid. Pricing comes after.

Why read it in a set order?

Because a tender pack is built for the person issuing it, not for you. The documents that decide whether you can or should bid are often the shortest and buried among the drawings and specifications.

A 22-page tender document with seven different attachments
Owner, fire protection and general construction firm, 14 workers, Kent coast

That was for a loft conversion. A pack that size is normal now, even for modest jobs, and reading every page before deciding whether to bid is how owners lose weekends to work they were never going to win.

What should you pull out in the first 10 minutes?

The items below, in this order. Note each answer on one page. If anything on the list is a deal-breaker, stop there.

The 10-minute tender read, in order

Ten items in ten minutes is a minute each. You're reading to find answers, not understanding every clause.

Where do you find each of these in the pack?

In most packs, the same few documents carry the answers.

You wantUsually in
Deadline, returns, questions, scoringInstructions to tenderers or invitation to tender
Scope, drawings, specScope of works, drawing register, specification
Form of contract and amendmentsContract particulars, schedule of amendments
Payment and retentionContract particulars, or subcontract order terms
ProgrammeTender programme or preliminaries
Rule-outsInstructions to tenderers, selection questionnaire

If you're bidding to a main contractor rather than the client, the subcontract terms may be a separate document from the main contract. Ask for them if they're missing; payment terms and retention sit there. For public sector work, the scoring and conditions of participation must be published with the tender notice, so they'll be in the pack. See the Procurement Act guide for small contractors.

What makes a tender a no-bid?

Anything you can't meet, can't price safely, or that pays too slowly for your cash. Decide before you measure anything.

  1. You can't meet a pass/fail requirement.

    Turnover, insurance cover, an accreditation or a reference you don't have. Check whether equivalents are accepted before giving up.

  2. The information isn't there to price it.

    Drawings missing, scope vague, no site visit allowed on a refurbishment. You can bid with heavy qualifications, but price the risk.

  3. The contract moves risk you can't carry.

    Design responsibility on a labour-only package, uncapped damages, pay-when-paid wording.

  4. The cash doesn't work.

    Long payment terms plus retention on a job that's a big share of your turnover.

  5. You're making up the numbers.

    Too many bidders, or a client known to go on price alone when your strength is quality.

What does pricing a tender cost you?

More than most owners think, because you pay for the ones you lose. The fair way to count it is the cost of one tender divided by the share you win.

Worked example

What one won tender costs a builder who pays a QS

A five-person builder prices a commercial fit-out. Owner's time valued at £45 an hour; a quantity surveyor prices the package.

Owner's time reading, visiting and checking12 hours × £45£540
QS fee to price it£1,250
Cost of one tender£1,790
Win rate1 in 520%
Cost of each tender won£1,790 ÷ 0.20£8,950
The QS fee is illustrative. Use your own fee, hours and win rate.

That £8,950 has to come out of the margin on the jobs you win. A builder who reads ten packs fully and prices every one is paying for nine he doesn't need to. A ten-minute read that rules out half of them is the cheapest saving there is. For the full sum, see the real cost of tendering, and if you're weighing up the QS, do you still need a QS.

Calculator: What one won tender costs you
hrs
£
£
%
Cost per tender won–

Your numbers, not a promise. Change any figure to match your firm.

What should you note down as you read?

Every gap, assumption and risk, in a running list. That list becomes your qualifications and exclusions when you submit, which protects the price you've worked out.

Typical notes from a first read:

  • "Drawing A-104 listed but not in pack"
  • "Asbestos survey not provided; assume none"
  • "Spec calls for a product brand; equivalent not stated"
  • "Working hours 8am to 4pm, Monday to Friday, occupied building"
  • "Retention 5%, half released at practical completion"

Turn those into clear wording with the tender qualifications and exclusions template.

When should you price it yourself versus send it out?

Price it yourself when you know the work and the drawings are clear. Send it to a QS or estimator, or use take-off software, when the measurement is big or outside your trade. Either way, do the ten-minute read first so nobody spends money on a tender you'd never bid.

One national groundworks firm we spoke to, seven staff plus subbies on mainly commercial work, ran everything on pen and paper and said he'd had "seven suppliers for a three-day job". The read is where you spot that kind of buying work before it eats your week. For measuring, see how to measure PDF drawings and the quantity take-off guide.

Where Nexley fits

Nexley is the AI back office for UK trade firms: five AI assistants run your tenders, quotes, buying, scheduling and invoicing. It connects to the tools you already work in, you run it all from WhatsApp, and you approve everything. £799 a month.

For tender packs, Nexley reads every document you forward on WhatsApp and sends back the deadline, return list, contract terms, payment and retention, scoring and any rule-outs in one summary, then drafts the take-off and priced schedule from your rates with a list of gaps to qualify. You decide whether to bid and approve the price.

Common questions

How long should it take to price a tender?

It depends on the size and the drawings. Count your own hours for the last few tenders and use the calculator above. The decision to bid should take about ten minutes; the pricing takes as long as the measuring.

Can AI read a tender pack for me?

It can pull out dates, scoring, terms and missing documents quickly, but you still check the result and own the price. See how AI reads a tender pack and what you still check.

What if the pack has no drawings?

Ask for them before the clarification deadline. If they don't arrive, price on stated assumptions and list those assumptions as qualifications, or don't bid.

Should I always do the site visit?

If one is offered on a refurbishment or any job with existing conditions, yes. On public tenders a visit is sometimes compulsory and missing it rules you out. See pricing a tender without a site visit if you can't attend.

Sources

  1. GOV.UK: Guidance on time periods (Procurement Act 2023)
  2. GOV.UK: Guidance on assessing competitive tenders
  3. GOV.UK: Guidance on conditions of participation

Every rule, rate and date above was checked against these sources on the date shown at the top.

Topic: Tendering and estimating

Keep reading

Tendering and estimating

AI tendering for roofers

Roof tenders are won and lost on the rate per square metre and the risks hidden behind it. This guide prices a 420 m² flat roof line by line, gives you a quick check for per m² or per day, a calculator and a qualifications list to copy.

29 Oct 2026, 9 min read, Kade Dillon

Tendering and estimating

AI tendering for electricians

Electrical tenders are priced point by point, but the money is lost in what the points leave out. This guide works through a 1,200-point take-off, a quick check on design responsibility, a price-per-point calculator and clarifications to copy.

29 Oct 2026, 8 min read, Kade Dillon

Tendering and estimating

AI tendering for dryliners

Drylining tenders are priced per m² of partition, but the risk sits in the system spec. This guide prices a 380 m² partition package, gives a quick check on substituting the specified system, a calculator and qualifications to copy.

29 Oct 2026, 8 min read, Kade Dillon

Try it on your own jobs

7 days free, then £799 a month. No contract.

Runs in WhatsApp Set up on a 20-minute call Cancel anytime
Saves me so much time every week. Does internal organisation and admin, but also when a customer messages in, Nexley replies, books them in against when I’ve got time to do it, and gets the invoice sorted in Xero.”
— Ollie Cable

Book a demo with Kade

A 20-minute call. Pick a time that suits and he’ll show you Nexley on your own work.

WhatsApp Us