Safety, certificates and compliance, 29 October 2026
Construction phase plan for small jobs, with a template
A construction phase plan sets out how health and safety will be managed on a job, and under CDM 2015 every construction project needs one before work starts, including domestic work. On a single-contractor job the contractor writes it; with more than one contractor, the principal contractor does. HSE says it should be proportionate: on a small job, two pages is often enough.
Do small jobs need a construction phase plan?
Yes. HSE's CDM guidance says CDM 2015 applies to all construction work, including domestic projects, and that if you're the only contractor or the principal contractor, you must draw up a construction phase plan. The plan should be proportionate to the size and scale of the job. HSE says a short plan prepared before work starts is usually enough to show you've thought about health and safety.
On domestic jobs the homeowner's client duties usually pass to you. HSE's summary of duties says domestic client duties normally transfer to the contractor on a single-contractor job, or to the principal contractor where there's more than one, unless the client agrees in writing that the principal designer will take them on. DIY work a householder does themselves isn't covered.
CDM 2015 covers Great Britain. Northern Ireland has its own CDM regulations with similar duties; check the NI version if you work there.
Who writes it on your job?
It depends on how many contractors will be on site, and a contractor here includes your subbies.
As the only contractor, you prepare the plan before work starts. On a domestic job you also take on the client's duties unless the client has agreed in writing that a principal designer will.
As principal contractor, you prepare the plan, share it with your subcontractors, and keep it up to date as the job changes.
Ask for the plan, read the parts that affect your work, and give them your RAMS and anything they need for it.
An electrician, plasterer and roofer on a loft conversion makes it a multi-contractor job, even if they're all self-employed and you've hired them. The person who runs the job for the client is normally the principal contractor.
What goes in a construction phase plan?
At minimum: the health and safety arrangements for the job, site rules, and specific measures for any work involving the particular risks listed in Schedule 3 of CDM 2015. HSE's CIS80 template turns that into a two-page form. The template below follows CIS80's headings and adds prompts that small builders tend to miss.
CONSTRUCTION PHASE PLAN Prepared by: your name, company, phone Date: date Version: 1 1. The job Client: name and address Site address: address What the job is: e.g. single-storey rear kitchen extension, 4 m × 5 m, with knock-through Designer or principal designer: name and contact, or "none" Principal contractor: name, or "single contractor: us" 2. What the client has told us e.g. asbestos survey from 2019 attached, garage roof contains asbestos cement; drains run under the patio; neighbour works nights 3. Key dates Start: date Finish: date Other: e.g. steel delivery, building control inspections 4. Welfare Toilet: e.g. client's downstairs WC agreed / hired unit Washing: hot and cold water, soap, towels: where Rest and drying area: where Drinking water: where 5. Who else will be on site trade, company, contact, dates 6. How we will keep everyone informed e.g. WhatsApp group for the job, briefing at start of each new stage, plan on the van dashboard 7. Site rules e.g. hard hats in the excavation zone, client and children kept out of the work area, site secured at end of day 8. Main dangers and how we will control them Falls from height: scaffold by a competent firm, inspected and tagged; ladders tied Excavations: shored or battered back; covers and barriers; spoil away from edge Collapse of structures: props and steel installed to engineer's design for knock-through Building dust: wet cutting, extraction, FFP3 masks Asbestos: survey seen; results shared with all trades; do not disturb garage roof Electricity and buried services: services located before digging; supply isolated before knock-through Members of the public, client and others: Heras fencing, signs, rubbish chute to covered skip Other: e.g. reversing deliveries on a shared drive 9. Supervision who supervises apprentices and new starters 10. Emergencies First aider: name First aid kit: where Nearest A&E: hospital Signed: name Read and understood by: names and dates
Keep the plan with the job, update it when the job changes, and make sure everyone on site has seen the parts that affect them. For the task-by-task detail, link it to your RAMS; our guide to site-specific RAMS from a master template shows how to keep those quick.
Does your job need notifying to HSE?
Most small jobs don't. A project is notifiable if the work is expected to last longer than 30 working days and have more than 20 workers working at the same time, or to exceed 500 person days. The client must notify, on form F10, though they can ask you to do it for them. HSE says to count every day work is likely to happen, including weekends and holidays.
Does a 12-week extension need an F10?
A single-storey extension and kitchen refit, 12 weeks, six-day weeks.
| Days work is likely to happen12 weeks × 6 days | 72 days |
| Most workers on site at oncegroundworks plus bricklayers | 6 |
| Test 1: over 30 days and over 20 workers at once?72 days, but 6 workers | No |
| Average workers on site per day | 3 |
| Person days72 days × 3 people | 216 |
| Test 2: over 500 person days?216 | No |
| Notifiable? | No |
Notification doesn't change whether you need a plan. You need one either way.
What's the quickest way to produce one?
Three free routes, from HSE and CITB:
- HSE's CIS80 is a two-page construction phase plan form. Print it or fill it on screen.
- CITB's CDM Wizard is a free app for iOS, Android and the web. You answer mostly tick-box questions in under five minutes, and it produces a construction phase plan you can view or email.
- Your own template, like the one above, kept in your job folder and copied for each job.
Whichever you use, the effort goes into section 8, the main dangers. A form with every box ticked "N/A" protects nobody.
When should you get help?
When the job involves structural alteration, deep excavation, demolition, or asbestos that has to be disturbed, get a competent person to check the plan. A structural engineer's design for temporary propping or a licensed asbestos contractor is part of the plan, not an extra. Moving into public sector work usually means clients will ask to see your plans, RAMS and policies at pre-qualification, so a health and safety adviser to check your templates once is money well spent.
Where Nexley fits
Nexley is the AI back office for UK trade firms: five AI assistants run your tenders, quotes, buying, scheduling and invoicing. It connects to the tools you already work in, you run it all from WhatsApp, and you approve everything. £799 a month.
Nexley keeps your construction phase plan template and drafts one for each job from what you send it on WhatsApp: the address, the scope from the quote, who's on site and a voice note about the hazards. You check it, change what's wrong and sign it before work starts. It also keeps the plan with the job file, so you can send it to a main contractor or council in one message.
Common questions
Does a domestic extension need a construction phase plan?
Yes. CDM 2015 applies to domestic projects, and the builder takes on the homeowner's client duties on most small jobs. As the only contractor or principal contractor, you must prepare a plan before work starts.
Is a construction phase plan the same as RAMS?
No. The construction phase plan covers health and safety for the whole job: welfare, site rules, who's on site and the main dangers. RAMS cover individual tasks in detail. Most jobs need both, and the plan can refer to the RAMS.
Is there a free construction phase plan template?
Yes. HSE publishes CIS80, a two-page construction phase plan template, and CITB's free CDM Wizard app produces a plan from tick-box questions in a few minutes.
Does a construction phase plan need to be sent to HSE?
No. You keep it and share it with those on site. Only notifiable projects need an F10 sent to HSE, and the F10 is a notification, not the plan.
Sources
- HSE: Summary of duties under CDM 2015
- HSE: CDM 2015 frequently asked questions
- HSE: Planning for construction work
- HSE: Construction phase plan template (CIS80)
- HSE: Are you a small builder?
- CITB: CDM Wizard
Every rule, rate and date above was checked against these sources on the date shown at the top.
Keep reading
Safety, certificates and compliance
Site-specific RAMS without two hours a job: working from a master template
Most of a RAMS is the same every time you do the same task. This guide shows how to split it into a master you write once and a one-page site sheet you fill in per job, with the master headings ready to copy.
Safety, certificates and compliance
F-gas certification for air conditioning installers
Installing split air conditioning means working on a refrigerant circuit, and that needs two certificates: one for the engineer and one for the business. This guide has a quick check for which you need, Refcom's fees worked out per year, and what electricians can and can't do.
Safety, certificates and compliance
Landlord EPC upgrades: what electricians and heating engineers can offer
Private landlords have until 1 October 2030 to bring rented homes up to EPC C, and work done since 1 October 2025 already counts. This guide sets out the rules, works through the £10,000 cap with a heat pump grant, and lists what electricians and heating engineers can offer.