Safety, certificates and compliance, 29 October 2026

Air conditioning and planning permission: when you need it

On a house in England, air conditioning usually doesn't need planning permission if the system also provides heating (an air-to-air heat pump), the outdoor unit is no bigger than 1.5 cubic metres, it meets the MCS 020a noise standard, and it isn't on a pitched roof or a listed building. Cooling-only units, commercial premises and conservation-area frontages normally need permission.

Why does heating make the difference?

Because the planning right is for heat pumps, not air conditioning. The permitted development right in England (Class G of Part 14 of the General Permitted Development Order) covers "microgeneration air source heat pumps". Until May 2025 it was effectively limited to units providing heat. The 2025 amendment changed the condition to "not solely used for the purpose of cooling", which brought air-to-air units that heat and cool inside the right.

So a reverse-cycle split system, sold and set up to heat the room as well as cool it, can be permitted development. A cooling-only unit can't. The Planning Portal puts it plainly: a cooling-only system needs planning permission.

What are the limits in England?

These come from Class G as amended on 29 May 2025. If any one of them fails, the install needs a planning application.

LimitRule
Number of unitsOne on a non-detached house or a block of flats; two on a detached house
Size of outdoor unitUp to 1.5 m³ including housing on a house; 0.6 m³ on a block of flats
NoiseMust meet MCS 020a; from 28 May 2026 the "or equivalent" route ended
RoofNot on a pitched roof; on a flat roof, at least 1 m from the edge
Listed buildings and scheduled monumentsNot permitted
Conservation areas and World Heritage SitesNot on a wall or roof fronting a highway, or nearer a highway than the house
ElsewhereNot on a wall fronting a highway above ground-floor level
Wind turbinesNot if there's already a wind turbine on the building or in the garden

The old rule that a unit had to be at least 1 metre from the property boundary was removed in 2025. Article 4 directions or planning conditions on a house can still take away permitted development rights, so check with the council if the house is on a new estate or in a sensitive area.

Run this on the survey

Ask these in order while you're on site. Most domestic jobs clear it in a minute.

Quick check: Do I need planning permission for this air con unit?
Is the property a house, or a block made up wholly of flats?
Will the system heat as well as cool?
Is the building listed, or a scheduled monument?
Does the outdoor unit meet MCS 020a and stay within 1.5 m³ (0.6 m³ on flats), with no other heat pump that would take it over the limit?
Will it go on the front, a pitched roof, or a wall facing the road above ground floor (or any road-facing wall in a conservation area)?
Likely permitted development

No application needed in England. Keep the MCS 020a calculation with the job file. If the customer wants certainty, they can apply for a lawful development certificate.

Planning permission needed

A cooling-only unit isn't covered. Offer a heat pump that heats and cools, or tell the customer to apply.

Listed building consent needed

Permitted development doesn't apply. The customer needs consent before anything is fixed to the building.

Planning permission likely needed

Move the unit, pick a smaller or quieter one, or tell the customer an application is needed before you book the install.

Check with the council

Class G covers houses and blocks of flats. Shops, offices and restaurants usually need planning permission for external units; councils often ask for a noise assessment.

What about shops, offices and restaurants?

Usually you need permission. Class G only covers houses and blocks of flats. Councils typically treat external air conditioning plant on commercial buildings as needing planning permission: one London borough's business guidance says permission is needed to install, alter, replace or move air conditioning where any part is fixed to the outside, and that noisy plant applications need a noise and vibration assessment. Check the local council's guidance before you quote a commercial job, and build the application time into the programme.

Is it different in Wales, Scotland and Northern Ireland?

Yes, so check where the job is before giving the customer an answer.

WalesScotlandNorthern Ireland
Can heat and cool?Yes, from 1 June 2026; not cooling-onlyMust be used only for heating or hot waterMust provide heat
NumberTwo on detached, one otherwiseOneOne
SizeUp to 1.5 m³No volume limit; up to 1 m from a wall or roofExternal unit up to 3 m high
Noise standardMCS 020aMCS or equivalentNot stated in the order
BoundaryNo fixed distanceNo fixed distanceNot within 1 m of a neighbouring house's boundary
Conservation areasNot on a road-facing wall or roofGround floor, rear onlyNot facing and visible from a road

From the Welsh Government heat pump planning page, Scottish Government Circular 1/2024 and the Planning (General Permitted Development) (Amendment) Order (Northern Ireland) 2023.

In Scotland, the right is for domestic heating, so a reverse-cycle unit installed mainly for cooling sits outside it. Ask the planning authority if in doubt.

Who should check, you or the customer?

Planning permission is the property owner's responsibility, but they'll ask you. Answering it on the survey, in writing, saves a lost job later.

Customers want accepting a quote to be simple, and planning is one of the questions they raise before they'll say yes. Put a line on the quote: "Installed as permitted development under Class G; assumes the property isn't listed, in a conservation area or subject to an Article 4 direction." It sets expectations and flags the cases where the customer needs to check.

You'll also need F-gas certification to fit the refrigerant side; see F-gas certification for air conditioning installers. For a site-specific RAMS for the install, see working from a master RAMS template. If the customer is a landlord, a heating-and-cooling heat pump may also help with EPC upgrades.

Where Nexley fits

Nexley is the AI back office for UK trade firms: five AI assistants run your tenders, quotes, buying, scheduling and invoicing. It connects to the tools you already work in, you run it all from WhatsApp, and you approve everything. £799 a month.

Nexley runs the survey questions for you. Send the address and a photo of where the outdoor unit will go on WhatsApp, and it drafts the quote with the planning line, the MCS 020a noise check details to fill in, and the RAMS, for you to check and approve. If the house is in a conservation area or listed, it flags it before the quote goes out.

Common questions

Do I need planning permission for air conditioning on my house?

In England, usually not, if it's a heat pump that heats as well as cools, the outdoor unit is 1.5 m³ or less, it meets MCS 020a and it isn't on a pitched roof, a listed building or a road-facing wall in a conservation area. Cooling-only units need permission.

Do I need planning permission for air conditioning on a flat?

A block of flats can have one heat pump under permitted development, with an outdoor unit up to 0.6 m³. Leaseholders will usually also need the freeholder's permission, which is a separate question from planning.

Has the 1 metre boundary rule for heat pumps gone?

Yes, in England. The amendment in force from 29 May 2025 removed the requirement for the unit to be at least 1 metre from the property boundary. Northern Ireland still has a 1 metre rule from a neighbouring house's boundary.

Does air conditioning on a shop need planning permission?

Usually. Permitted development under Class G covers houses and blocks of flats only. Check with the local council, which may ask for a noise assessment.

Sources

  1. legislation.gov.uk: GPDO 2015, Schedule 2, Part 14, Class G
  2. legislation.gov.uk: GPDO (England) (Amendment) Order 2025, SI 2025/560
  3. legislation.gov.uk: Impact assessment, amendments to the air source heat pump permitted development right
  4. Planning Portal: Planning permission for air source heat pumps
  5. Planning Portal: Do I need planning permission to add air conditioning to my home?
  6. Welsh Government: Planning permission, domestic heat pumps
  7. Scottish Government: Circular 1/2024, householder permitted development rights
  8. legislation.gov.uk: Planning (General Permitted Development) (Amendment) Order (Northern Ireland) 2023
  9. Lewisham Council: Planning FAQs for businesses

Every rule, rate and date above was checked against these sources on the date shown at the top.

Topic: Safety, certificates and compliance

Keep reading

Safety, certificates and compliance

Construction phase plan for small jobs, with a template

Under CDM 2015, the builder writes the construction phase plan on most small jobs, before work starts. This guide gives a fill-in template based on HSE's own, a worked example for a kitchen extension, and a quick check on notification.

29 Oct 2026, 8 min read, Kade Dillon

Safety, certificates and compliance

F-gas certification for air conditioning installers

Installing split air conditioning means working on a refrigerant circuit, and that needs two certificates: one for the engineer and one for the business. This guide has a quick check for which you need, Refcom's fees worked out per year, and what electricians can and can't do.

29 Oct 2026, 7 min read, Kade Dillon

Try it on your own jobs

7 days free, then £799 a month. No contract.

Runs in WhatsApp Set up on a 20-minute call Cancel anytime
I had a quick demo and we’ve never looked back. Nexley works, it’s simple, and we’re really happy. Just give it a try.”
— Pete Charley

Book a demo with Kade

A 20-minute call. Pick a time that suits and he’ll show you Nexley on your own work.

WhatsApp Us